(Updated 11th October 2000)

RVR CONSTRUCTION DIARY


On April 21st 2000 No 1 eases a construction train consisting of C and K wagons over the 
partially constructed Dragonrock bridge.

This page, like all the rest!, has a lot of photos and will take a while to load.

After a long period during which I have been too busy building! to update this section, this is what has been happening recently.

As of 11th October the main line has been extended from Bottom Points in a southerly direction 
(see TRACK PLAN) resulting in the construction of two major bridges and two new stations and changing the focal point of the line from the zig-zag to the new main line.  Once this section is completed, emphasis will change to rebuilding the zig-zag to eliminate to notorious 1 in 12 section at the top of the middle road.  This will take the form of a large loop on easier grades that will eliminate Top Points altogether, so bypassing the zig-zag altogether.
 

HAZARDS OF GARDEN RAILWAYS; 
EXPECTED............ and UNEXPECTED!

During November 1999, shortly after completion of the zig-zag and the final section of line to Devlins, Sydney suffered from a couple of weeks of torrential rain, and a large amount of ballast was washed away and in some sections the line was left hanging in mid air. 


The Bottom Road after the rain, ballast washed away on the left and severe scouring on the right at the entrance to Possum Creek 
station where natural drainage occurs.

In the best traditions of Australian bush railways temporary repairs were carried out with some logs and trains continued running while a more permanent solution was worked out!

The station platforms also suffered severely from the rain.

By May 2000 however, the damage had been repaired and (hopefully) will not recur.  Culverts and a small bridge were erected over the watercourses and a stone wall built along the length of the Bottom Rd.  In areas of severe loss of ballast, a 1 to 1 mix of ballast and cement was laid over the existing ballast, which seems to have cured the disappearing ballast problem.


A Tasmanian style wooden trestle over one of the drainage courses on the Bottom Rd and the two culverts at the entrance to the 
yard at Possum Creek.  The handrails are to prevent the shunters falling into the creek!  The stone wall now stretches all the 
way from Possum Creek to the new bridge at Dragonrock.


  Along with the expected Garden Railway hazards of falling leaves, falling branches and washaways caused by heavy rain, 
the RVR also has Dinosaurs!  (Well, up to 1 metre long Water Dragons can seem like dinosaurs in this scale!)  There is a resident population of these large reptiles living in the creek at 
the bottom of our land, and a couple of them seem to have 
become railway enthusiasts!  This photo shows one of the small ones inspecting the track on the Middle Road in late 1999, before the rain.  They hibernate during winter, but have now 
re-appeared, and have now taken to digging holes in the ballast!  They are probably looking for insects, (their main food source).

 

DRAGONROCK BRIDGE

After a break in new construction over the summer, (too hot and too many repairs to do!) the mainline was extended towards the swimming pool with the erection of Dragonrock bridge and station.


On the 21st April 2000 the installation of the Dragonrock bridge began.  The previous couple of weeks had seen the spans and trestles constructed in the workshops.  One of the spans can be seen on the construction train waiting on Bottom Rd.  The temporary station building at Devlins can be seen in the top right of the photo.
Consisting of two underslung Howe trusses and trestle approaches, and constructed from Tasmanian oak and sawn up fence palings, Dragonrock bridge, so named because the Water Dragons sun themselves on the rock to the left of the bridge, was substantially complete by April 22nd.  Bill Cooper's brand new Shay treads gingerly (Bill wasn't driving!) across the newly opened bridge later in May.  The bridge design was based on that of the original Quarter Mile bridge on the Mt Lyell line.  The reason for the use of this design of bridge on a side valley, where in full size an ordinary trestle would have been used, is because we need to maintain access to one of the compost heaps, which is directly behind the bridge.

 
DRAGONROCK SIDING & THE UNDERPOOL TRESTLE
 
 
Dragonrock siding consists of a simple loop, which is used at the moment to load firewood for the Possum Creek smelter.  There will, eventually, be a small shelter and platform.  Here F5 and FF16, loaded with firewood, wait to be picked up by the next Down train.
 
To take the line from Dragonrock around the end of the pool and into Underpool station a typical Mt Lyell style trestle bridge is 
been constructed.  However, on the 8th September, construction 
of the bridge had not started, but trains were running into 
Underpool via this "Contractor's bridge" consisting of a couple of sticks holding the track up.  The staff were not impressed!  Here 
No 1 carefully traverses this flimsy structure with a works train, keeping very closely to the 3mph speed limit!  Trains ran over this bridge for about 2 months while the permanent bridge was constructed.

MAKING THE RVR "SHAY FRIENDLY"

As many modellers have found out, the Bachmann Shay is BIG!  The only section on the RVR that has been a problem however, is the tunnel on the middle road, which was just slightly too narrow for the Shay.  The problem first reared its ugly head when Graham Morphett visited in March, but with the conversion of Bill Cooper to large scale, (Bill lives about 10 minutes walk away, and is a regular visitor) it was deemed appropriate to do something about that narrow tunnel!


A few minutes work on the inside of the tunnel with a
hammer and cold chisel and the tunnel was wide enough 
for the Shay
Tom inspected the work to make sure that Dad had done it right!

 


 
RVR BUILDINGS

The RVR has managed to aquire a few buildings, with more on the way.
 

The first building to be completed was the station building at Bottom Points.  It was based on one of the buildings that used to stand at Teepookana on the Mt Lyell line, though much condensed and adapted.  It 
was constructed of timber and corrugated aluminium over a plywood box, my standard system for constructing buildings.
 
Possum Creek's goods shed, constructed from corrugated aluminium cans and styrene over a plywood box.  It is based on a condensed version of a standard Tasmanian Government Railways goods shed.

 
VIEWS OF THE LAYOUT DURING EARLY CONSTRUCTION

Here are a few views of the layout taken in 1999.
 

The AME carefully backed the, as yet, unpainted  RVR No1 up the hill with the works train when the newly laid Middle Road was being tested on 26th August 1999.  In the foreground is the original retaining wall, made from Privet sticks, a pestilent weed that infests our block and the surrounding bush.  It has now been replaced with a stone wall and a bridge, while a culvert and timber retaining walls have been constructed on the Middle Road.  The section above the train is the infamous 1 in 12 grade that will be replaced with a deviation in the near future.
   
Looking back down the Middle Road on the 21st September 1999 with the AME carefully backing the train down under RCS radio control.  Once I joined the LGB and G Scale Club of Australia, I was able to continue tracklaying along the Top Road towards the next station, Devlins, thanks to the Club's supply of cheap "Club Rail"!  The deviation will result in what was the Middle road arriving at Top points a couple of inches lower on the same formation, swinging out to the left and behind the photographer on a completely new formation and reappearing on the right of the photo and proceeding around to Devlins where it will rejoin the current formation.  The site of Dragonrock bridge can be seen at the far end of Bottom road.
 
An overall view of the layout as it existed on 26th August 1999 from the "lookout" at the top of the hill.  The Assistant Mechanical Engineer is driving RVR No 1 under radio control as it hauls 2 four wheel and one bogie flat wagon up the bottom road to the worksite on the middle road, the formation of which can be discerned to the left of the train.  This formation was laid out with the string and sticks method that appears to be the way everyone does things in this gauge, after earthmoving took place a layer of weed cloth was laid and then a layer of ballast was spread over the top.  The track, which had already been soldered into 2 metre lengths and painted was then laid and the connecting fishplates between the 2 metre lengths soldered together.  After final alignment and levelling, (or in this case, final 1 in 12ing!) ballast was dropped and spread with an old brush.  Experience has shown that the weed cloth is worse than useless, it doesn't prevent weeds, but it does allow the ballast to be lost more easily, so I no longer lay weed cloth under new construction.  I have also modified my use of loose ballast, as mentioned above, using a 1:1 mix of ballast and cement in areas subject to excessive water runoff.  Working out the levels is now a lot easier since I constructed a "water level" as per the recent article in "Garden Railways".
   
Back to the beginning, 23rd July 1999,  6 weeks after we moved in! This photo taken on the first day of construction shows the site of Bottom points with the first couple of metres of temporarily laid track.  The RVR's first loco, RVR No 1, (before conversion from an LGB Stainz) and a Lehmann flat stand waiting for somewhere to go!  Now  the zig-zag is finished and the main line continues towards Dragonrock over the bridge outlined above, past the siding at Dragonrock and around under the pool on a large trestle bridge. 

 
Lambing Flat Home Page
Rurr Valley Railway Title Page
Lambing Flat Layout Page
RVR Layout Description
RVR Locomotives
RVR Rolling Stock